CPEC’s US $1,780 million Karot Hydropower Project to be completed in April 2022: CPEC Authority chief
Gwadar Pro
Islamabad: China-Pakistan Economic Corridor (CPEC) Authority chief Lt. General Asim Saleem Bajwa (retd) has said that US $1,780 million Karot Hydropower Project under CPEC will be completed in April 2022.
He said that 88 percent of the work on the Karot Hydropower Project had been completed. The hydropower project – the first of its kind under the CPEC – is being built on the River Jhelum, he said in a tweet.
The project is being developed on a Build-Own-Operate and Transfer (BOOT) basis at an estimated cost of $1.98bn including a development cost of $1.698bn and interest during construction of $243m by Karot Power Company Private Ltd, comprising of M/s Three Gorges South Asia Investment Ltd (TGSAIL) and Associated Technologies (Pvt) Ltd of Pakistan.
The project is being constructed on a concrete gravity of 91 metres high dam with a crest length of 320 meters near the village of Gohra. The dam’s reservoir will be approximately 152m cubic metres in volume, with a length of 27 kilometres. Around 72 homes and 58 businesses were expected to be relocated due to project construction while 2.8-km of the Karot-Kotli road and 8.9-km of the Azad Pattan-Kahuta road were expected to need relocation.
Bajwa said the investment amounted to $1,780 million while 5,000 local people were directly employed for its construction.
The 720-megawatt Karot Hydropower Project was initially due to be completed in 2020. It has the capability to generate 3.249 billion units of clean electricity per year for the national grid.
The National Electric Power Regulatory Authority (Nepra) had in February 2016 approved the project’s levelised tariff at 7.57 cents per unit for 30 years at an exchange rate of Rs 101.6 per US dollar. Its groundbreaking ceremony was held in January that year.